Description:
title
Discuss, consider and/or take action to authorize the County Judge to sign Change Order #4 with Oprex Construction, LLC in the amount of $3,554.91 and 16 additional days for the Juvenile Justice Center Academic Addition project.
body
Comment:
This change order adds $3,554.91 to the project and 16 days. Total project cost now sits at $3,576,814.76.