Title: Discuss, consider and/or take action to authorize the County Judge to sign Change Order #4 with Oprex Construction, LLC in the amount of $3,554.91 and 16 additional days for the Juvenile Justice Center Academic Addition project.
Related files: 23-0540, 23-0285, 22-0631, 23-0047

Description:

title

Discuss, consider and/or take action to authorize the County Judge to sign Change Order #4 with Oprex Construction, LLC in the amount of $3,554.91 and 16 additional days for the Juvenile Justice Center Academic Addition project.

body

Comment:

This change order adds $3,554.91 to the project and 16 days. Total project cost now sits at $3,576,814.76.