Discuss, consider and/or take action to authorize the County Judge to sign the first amendment to the contract for constructions with MH Civil Constructors, Inc. for the Lubbock County Detention Center Sewer Screen project.
body
Comment:
This amendment was authorized and the additional scope exempted by Court on May 27th. Additional cost of $309,333.00 for the grinder and an additional 154 days once the grinder is delivered (lead time is 13 weeks).