File #: 24-0811   
Type: Change Order Status: Passed
File created: 9/17/2024 In control: Commissioners Court Regular Meeting
On agenda: 9/23/2024 Final action: 9/23/2024
Title: Discuss, consider and/or take action to authorize the County Judge to sign Change Order #5 with Lee Lewis Construction, Inc. for the Court Residential Treatment Center-Phase IV in the amount of $111824.77 and 38 additional days.
Attachments: 1. Change Order Attachment
Related files: 25-0230

Description:

title

Discuss, consider and/or take action to authorize the County Judge to sign Change Order #5 with Lee Lewis Construction, Inc. for the Court Residential Treatment Center-Phase IV in the amount of $111824.77 and 38 additional days.

body

Comment:

This change order covers added camera cabling w/ ceiling patches ($68,843.55), added County IT Rack and ladder add w/credit ($8,421.09), IT Cable Relocations ($33,487.13 and 15 days), and additional IT twist lock receptacle($1,073.00).