Description:
title
Discuss, consider and/or take action to accept the Guaranteed Maximum Price (GMP) and Contract Time for the New Collaborative Law Enforcement Center as proposed by the Construction Manager-At-Risk, Lee Lewis Construction, Inc. and ratify the signing of Amendment One to the Construction Manager-At-Risk Agreement setting forth the accepted GMP and time.
body
Comment:
Lee Lewis proposes a Guaranteed Maximum Price of $18,371,095 with the below breakdown.
Administration & Garage (Building A) $16,331,146
K-9 Facility (Building B) $895,494
Impound Garage (Building C) $1,144,455
Substantial Completion is proposed to be 16 months from the building permits being issued.