Description:
title
Discuss, consider and/or take action to authorize the County Judge to sign Change Order #4 with Henthorn Commercial Construction for the 916 Main, 3rd Floor Renovation project, in the amount of $26,770.89 and an additional 20 days.
body
Comment:
This CO brings the amount of COs to $108,274.96 and moves the substantial completion date to June 1, 2024. This CO adds electrical and HVAC scope to the project.