Discuss, consider and/or take action to authorize the County Judge to sign Change Order #1 for the 916 Main Street 3rd Floor Renovation with Henthorn Commercial Construction in the amount of $7,121.40 and 5 days.
body
Comment:
This brings the total of the project to $2,142,121.40 and 250 days. This CO includes the relocation and rerouting of fire line pipe that was discovered during demolition. Also addresses removal of existing mechanical room ceiling and modifications to existing sprinkler heads for proper coverage and support.