Discuss, consider and/or take action to authorize the County Judge to sign a Letter of Agreement with Ranger Fire, Inc. for the Lubbock County Detention Center Fire Pump Replacement project as awarded in ITB 230601 on July 24, 2023.
body
Comment:
This agreement gives the Owners Representative (Natalie Harvill) change order authorization up to $10,000 as allowed in LGC 262.031(b). Total cost of the project is $202,000.00 and 120 days.