Description:
title
Discuss, consider and/or take action to authorize the County Judge to sign Change Order #1 with Dennard Construction for the Courthouse West Entry Accessible Ramp in the amount of $24,860.00 and 56 additional days.
body
Comment:
This brings the contract to a total of $$179,860.00 and a new substantial completion date of June 26, 2024.