File #: 23-0008   
Type: Contracts and Agreements (MOU, Statement of Work) Status: Passed
File created: 10/12/2022 In control: Commissioners Court Regular Meeting
On agenda: 10/24/2022 Final action: 10/24/2022
Title: Discuss, consider and/or take action to authorize the County Judge to sign Change Order #2 for an additional 273 days and $4,025.00 with Hub City Plumbing & Mechanical for the Lubbock County Detention Center Domestic Water Boiler Replacement project.
Related files: 22-0189, 24-0033

Description:

title

Discuss, consider and/or take action to authorize the County Judge to sign Change Order #2 for an additional 273 days and $4,025.00 with Hub City Plumbing & Mechanical for the Lubbock County Detention Center Domestic Water Boiler Replacement project.

body

Comment:

This change order will bring the total of the project to $429,831.00 with substantial completion now scheduled for October 31st.  This change order is the only increase in amount for the contract.