Description:
title
Discuss, consider and/or take action to authorize the County Judge to sign Change Order #2 for the 916 Main Street 3rd Floor Renovation with Henthorn Commercial Construction in the amount of $44,814.00 and 10 days.
body
Comment:
This brings the total of the project to $2,186,935.40 and 260 days. This change order is for the application of spray applied fire resistive protection and the structural steel components and deck of the 4th floor per IBC 2015 and Life Safety requirements.